Contract Amount: 340 M THB
Contract Period: June 2017 to October 2018

Fabrication & Erection of Structure work
- 610 tons

Fabrication & Erection of Piping work
- 56,000 DB

Civil work
- Concrete 11,000m3

Mechanical Work
- GTG Compressors
- Ground Flare
- Gas & Lube Oil Coolers
- Inlet filters, fire fighting pumps
- Air compressor station
- Fuel Gas Skid

Painting & Insulation Work